| Year of completion : 2009 |
|
|
|
| Engineer (Consultant) : |
|
|
| Funded by : |
|
|
| Geo Location : |
 |
|
| |
| This building construction project, namely the “Mahamaya Girls school at Matara” was constructed to the highest quality within expected cost and to the scheduled time period. |
|
| UNICEF being the funding agency and the “Employer” of the contract awarded this contract to us on November 28, 2008. The client appointed “Kahawita de Silva Associates (Pvt) Ltd” as the Engineer of this contract. We started construction works in December 2008 and proceeded well with the hope of completing works by December 2009, the intended completion of this contract of 12 months duration.successfully completed on January 18, 2010. |
|
| However due to variations, the time for completion was extended up to January 25, 2010 and we completed works satisfactorily on January 18, 2010. |
|
| The project consisted of construction of a new school as a post – Tsunami Construction Project which included three numbers three storied school buildings, three numbers single storied buildings, external works and a shrine room. |
|
| The total floor area of the buildings was 35,500 sq.ft. |
| |